Detailed Engineering, Procurement and Construction of third LNG Tank of 95.000 M3 storage capacity
Price
98 million Euros
Period
06/2013 - on going (construction period 34 months)
The project consists of the detailed engineering (i.e. process, process safety, civil, structural, mechanical, equipment, electrical and I&C design), procurement of materials and equipment, construction, commissioning and initial operation of a new LNG tank (full containment type) of 95.000m3 net capacity and its inter-connection with the existing unloading and degasification facilities as well as with the existing electrical network the DCS and ESD of the plant, the fire and gas detection systems, the fire fighting network and the utilities network.